The partial interior demolition of the Royal Connaught that was abandoned halfway through exposed many parts of the building to an increased chance of water infiltration which, as the seasons passed, resulted in accelerated mold growth. Particularly noted on the main and 2nd floor boardroom and office areas. The water from the upper levels more freely flowed down toward the main and 2nd floors as the regular drainage systems were interrupted or completely removed in anticipation for replacement.

The Lister Block was arguably in even worse condition than the Royal Connaught is now, as the building had over a decade to be subjected to arson, vandalism and the natural elements. I guess the bottom line there was that anything is possible when you have $30 Mil of public money.