Here's the math with new numbers from Mark Masters' National Post article. (BTW, he's been doing a great job on this story)

Ivor Wynne rebuild budget breakdown
(All figures in millions)

COSTS
South stand construction (approx 15,000 seats) — 138.2
North stand renovation (approx 10,000 seats) — 10
Demolition and site preparation — 4
Replace Brian Timmis Stadium — 2.4
Total — 154.6

FUNDING SOURCES
Toronto 2015 (provincial and federal governments) — 69.1
City of Hamilton — 51.5
Stadium naming rights — 6
Hamilton Tiger-Cats — 3
Total — 129.6

Total funding shortfall — 25



Read more: http://sports.nationalpost.com/2011/01/27/funding-gap-for-ticats-stadium-shrinks/#ixzz1CIdKpVjT