You are correct (see item 9 in article). This fact was recently revealed to Council and is just one of many items that will make the overall success of the Aerotropolis questionable. Here is a BIG one;

There are no stormwater sewers planned for the AEGD and ALL stormwater must be managed on site. At one of the CLC meetings the consultants presented various options for stormwater management that fit within the "eco-industrial" plans for the AEGD - estimated costs per acre depending on method used is $100,000 to $1,000,000.