By Haveacow (registered) | Posted September 22, 2016 at 16:53:48

As your councilors continue to interfere... Today in Ottawa the first section of OCS (Overhead Catenary System), the electric wires that power the LRV's for the Confederation LRT Line, got turned on today at 10:30 AM to begin the testing of LRV's. Belfast Yard maintenance and Storage facility OCS wires were fully energized and tested today. Then over the next few weeks OCS sections going up the access track to the mainline and then west to the edge of Trembley Road Station. By late October all the OCS sections heading east all the way to Blair Station will be fully energized. All the LRT stations from Trembley Road east to Blair themselves won't be fully complete until February 2017. A few of them however, are ahead of schedule!

http://www.octranspo.com/about-octranspo...